Bus shelter for the 99 B-Line coming to Commercial-Broadway Station!

A rendering of what the completed bus shelter for the 99 B-Line will look like at Commercial–Broadway Station.

As part of the ongoing upgrades to Commercial–Broadway Station, a large, bus shelter to serve the 99 B-Line will begin construction next week and continue into the new year. The bus shelter will provide weather protection to approximately 160 passengers standing in the queue – a welcome addition on those notoriously rainy Vancouver days!

The bus stop at Commercial-Broadway for the 99 B-Line is the busiest on the entire transit network, and serves as one of the most important transit interchanges in the region. The 99 B-Line attracts more riders than any other bus corridor in Canada or the United States with more than 17 million annual boardings, and Commercial-Broadway Station is the busiest SkyTrain station in the system.

This project was made possible in partnership with the federal government through the Public Transit Infrastructure Fund (PTIF).

Author: Terence Chu

Running Rail Replacement work May 25–May 30, 2017

Modified service route 1 NW to VC_17x11-01
We are continuing with our work to replace 7,000 aging rail pads and 5,000 linear metres of running rail on the Expo Line.

This phase of the Running Rail Replacement Project began this February and will continue through summer 2017.

This batch of work will include single tracking later in some evenings as well as some morning and afternoon work on the weekend.

On May 27 and May 28, two sections of track west of Main Street–Science World Station will require extended times to accommodate the necessary special treatment to pre-bend the 60 foot rail sections before installation.

Please take note of the schedules below and know before you go!

Thursday May 25 & Friday May 26

  • From 9:30 pm until the end of service

Saturday May 27

  • From start of service until 2:00 pm AND
  • From 11:30 pm until the end of service.

Sunday May 28

  • From start of service until 3:00 pm.
  • There will be no single tracking Sunday evening.

Monday May 29 & Tuesday May 30

  • From 9:30 pm until the end of service.

For all affected service days:

  • Expo Line trains will use one track in both directions at Main Street–Science World and Commercial–Broadway stations.
  • Expo Line passengers should allow for 15-20 minutes extra travel time.
  • All Expo Line trains will operate between Waterfront and King George stations.
  • Expo service to Sapperton, Braid, Lougheed Town Centre and Production Way–University will be replaced with trains operating between New Westminster and VCC–Clark. Passengers from other stations on the Expo Line can change trains to this service at Commercial–Broadway, New Westminster and Columbia stations.
  • Millennium Line and Canada Line will operate normally.

This work schedule is subject to change.

Learn more about our Running Rail Replacement Project!

Have questions about this project or single tracking? Ask away!
Tweet @TransLink or call 604-953-3333.

Author: Adrienne Coling

Running Rail work continues on the Expo Line

The Running Rail Replacement Project continues with work near Main Street–Science World Station is starting April 2. Work will not be done on Fridays and Saturdays and is weather dependent.

From 9:30pm until the end of service, Expo Line trains will be single tracking – when trains travel on the same track in alternating directions – between Main Street-Science World and Commercial-Broadway stations.

Expo Line trains will operate between Waterfront to King George Station. Please be aware that during this work, there will be no Expo Line trains to Production Way–University.

There will be a shuttle train operating between New Westminster and VCC–Clark. You can change trains to this service at New Westminster and Columbia stations.

map
If you are travelling on the Expo Line, please allow for 15-20 minutes extra travel time. Millennium Line and Canada Line will operate normally.

Tips for a faster trip using Special SkyTrain Service

  • If you are travelling from downtown Vancouver and your destination is Sapperton, Braid, Lougheed Town Centre or Production Way–University stations, take an Expo Line train to Commercial–Broadway station and change trains to a VCC–Clark – New Westminster train operating from platform 2.
  • If you are travelling from Commercial–Broadway to Braid, Sapperton, Columbia or New Westminster stations, board a VCC–Clark – New Westminster train operating from platform 2.
  • If you are travelling from New Westminster Station to a destination along the Millennium Line, including Commercial–Broadway Station, take the New Westminster – VCC–Clark train.
  • If you are travelling from Surrey to a destination along the Millennium Line, including Commercial–Broadway Station, ride the Expo Line to Columbia and transfer to a New Westminster – VCC–Clark train.
  • If you are travelling on the Millennium Line Evergreen Extension to New Westminster Station or beyond, transfer at Lougheed Town Centre as you normally would and catch the VCC–Clark – New Westminster train from Platform 2 at Lougheed Town Centre. If required, change to the Expo Line at New Westminster to continue west.

Schedule Adjustments due to events

  • Sunday April 2: Service change delayed one hour, beginning at 10:30pm, to accommodate the Canucks hockey game.
  • Wednesday April 5: Service change delayed one hour, beginning at 10:30pm, to accommodate the Canucks hockey game.

Thank you for your patience during this necessary maintenance to our SkyTrain system.

Know before you go!
For more information on what this means for your commute, visit translink.ca/alerts.
Find details on the Rail Replacement Project at translink.ca/rail replacement.

Author: Adrienne Coling

Temporary closure of the Commercial-Broadway south elevator

Commercial_Sign
**UPDATE** March 21, 2017

This work has finished ahead of schedule and the elevator is in service.

Upgrades to Commercial–Broadway Station are well underway. The next phase of construction will start next week, with crews completing necessary upgrade work on the elevator.

From March 6 to April 3, the south elevator to platforms 3 and 4 will temporarily close for demolition and construction in the elevator machine room. Current elevator code restricts work in the machine room, while the elevator is in service.

The existing elevator on the north side of the station, and all escalators will continue to be in service.

How do I get to the other elevator?

From the platform, elevator users will have to cross the overhead walkway over Broadway and take the elevator down to the concourse level, and cross the street, if needed to access the south (Safeway) side of the station.

From street level, customers can use the north station entrance (next to Shoppers Drug Mart), tap at the fare gates and access the north station elevator.

Passengers requiring assistance can use the red emergency phone or ask for assistance from a SkyTrain attendant.

Signs are posted throughout the station and at station entrances to let customers know about this temporary change.

What work is happening?

Construction inside the machine room includes:

  • Assembly and installation of an enclosure within the machine room.
  • Partial demolition of walls and floors.
  • Installation of new elevator equipment.

When complete, the larger machine room will contain new equipment to power one additional elevator that will provide service between the new platform and the concourse.

Why are we doing this work during service hours?

Completing work when the trains aren’t running will only provide a few hours of work time.

If we complete this work for a few hours each night, it will delay overall construction at Commercial-Broadway Station. A delayed work schedule would have a significant impact on our customers.

Building an enclosure in the elevator room allows crews to work and still provide service to the elevator. The other option meant closing the elevator for six months while the construction in the machine room was complete.

We recognize that this is a major impact to our customers and we thank everyone for their patience while we improve Commercial–Broadway Station.

You can find more information about this upgrade work at translink.ca/commercialbroadway.

Author: Jessica Hewitt

Upgrades to the Commercial–Broadway pedestrian walkway are underway!

Rendering
We’re making major improvements to the pedestrian walkway at Commercial–Broadway Station to better connect you to Millennium Line platforms from the Expo Line.

To do this work, the pedestrian walkway to the Millennium Line trains (Platforms 1 and 2) at Commercial–Broadway Station will narrow.

Construction crews will partially demolish and reconstruct the existing walkway over the Grandview Cut.

The crossing will be narrowed through various phases. At the narrowest, the walkway will be reduced by 1.5 metres.

When construction is complete, the new pedestrian walkway to Platforms 1 and 2 will be 14 metres wide, roughly doubling the existing space for one of our busiest stations!

Details:

  • Access to the station and from the platform will not change. Customers can continue to use the stairs, escalators and elevators to access the platform.
  • The walkway narrowing will not affect SkyTrain service.
  • Hoarding has been put up along the entire length of the walkway. Additional lighting will be installed to ensure the area is well lit.

Station upgrades include:

  • New east platform serving westbound Expo Line trains.
  • New pedestrian walkway over Broadway, connecting the platform to the Millennium Line platforms and the westbound 99 B-Line stop.
  • Permanent queuing system and bus shelter for the 99 B-Line stop.
  • Widening of the walkway that provides access to the north station platforms (Platforms 1 and 2).
  • Two new elevators and four escalators (two going up and two going down from the platforms).
  • Expanded Broadway concourse.
  • Widened Broadway entrances to the Broadway Station.
  • New retail spaces in Broadway Station.
  • Replacement of mesh panels with glazed panels at platform level.
  • New lighting design to respond to specific conditions in the station.
  • New bike storage room that will accommodate 70+ bikes.

Rendering 2
Crews will work around the clock to minimize the impact of this construction but passengers should allow for extra travel time – especially during peak periods – until the walkway work is completed.

For more information on this project, call 604.953.3333
or visit translink.ca/commercialbroadway.

Author: Adrienne Coling

Construction work continues on the SkyTrain system

Commercial Station by Dana Lu.

Commercial–Broadway Station by Dana Lu.

**UPDATE** Due to weather conditions, the work at Commercial–Broadway Station was delayed. The pedestrian walkway to the Millennium Line trains (platforms 1 and 2) at Commercial–Broadway will narrow starting this Sunday, February 19th.

We are working hard to ensure our system meets the needs of our customers. You may have seen, or heard, crews at Stadium-Chinatown and Commercial-Broadway stations working over the last few days and weeks.

Stadium–Chinatown sign installation

You’ve told us that you wanted more signage on the system and we are working away to make this happen. We’ve installed new signage at virtually every platform at Expo and Millennium Line stations.

2013-10-03_ST_006

Fencing and signage before

Inlet trackside

What fencing and signage will look after completion

Right now, construction crews are installing a new fence to mount new directional signs at Stadium–Chinatown Station.

To ensure our customers know where to go when they are on the train, we’re installing trackside rails and fences to mount large signs.

If you’ve been on the Evergreen Extension, you’ll see similar fencing and signs installed between platforms.

These signs are essential so customers can see what station they are arriving at and the route of the train. This work will continue on Sunday to Thursday nights between the hours of approximately 2 a.m. and 5 a.m. over the next couple of weeks.

Residents in the area may hear nighttime noise as this work can only be completed when trains are not running. If we did this work during the day, this would mean we couldn’t provide service to Stadium–Chinatown Station.

We recognize that this work has an impact on residents who live near the station and we thank everyone for their patience while we make these improvements.

Upgrades continue at Commercial–Broadway Station

commbway_stn_rendering
Beginning in early February, the pedestrian walkway to the Millennium Line trains (platforms 1 and 2) at Commercial–Broadway Station will narrow.

Construction crews will partially demolish and reconstruct the existing pedestrian walkway over the Grandview Cut.

The crossing will be narrowed through various phases. At the narrowest, the walkway will be reduced to just over four metres wide. When construction is complete, the new pedestrian walkway to platforms 1 and 2 will be 14 metres wide!

Details:

  • Access to the station and from the platform will not change. Customers can continue to use the stairs, escalators and elevators to access the platform.
  • The walkway narrowing will not affect SkyTrain service.
  • Hoarding will be put up along the entire length of the walkway. Additional lighting will be installed to ensure the area is well lit.
  • Please allow for extra travel time when connecting through Commercial-Broadway Station. Customers should expect some additional crowding at the station during peak times.

When complete, the station will include:

  • An additional platform for Expo Line trains, a widened crossing over the Grandview Cut and a new pedestrian walkway over Broadway.
  • New elevators and up and down escalators to improve access for customers with disabilities.

Together with the contractor, we are making every effort to minimize the impact of this construction activity. Crews will work around the clock to ensure that the upgrades are completed as quickly and safely as possible for the benefit of residents and users of the SkyTrain station.

Construction is expected to be complete by next winter.

We thank our passengers and neighbours for their patience as we make these much-needed improvements.

If you have questions or concerns about these projects,
please reach out to Customer Information by phone 604.953.333 or on Twitter.