New bus loop at Joyce-Collingwood Station and more!

The TransLink Maintenance and Repair Program is improving aging infrastructure across the system

Upgrades to Joyce-Collingwood Station are well underway. The new bus loop at Joyce-Collingwood Station is now complete – a milestone in the TransLink Maintenance and Repair Program that’s improving aging infrastructure across the system.

The next phase of construction will start next week, with crews completing necessary upgrade work.

The west stationhouse at Joyce–Collingwood SkyTrain Station will be closed from August 13 until spring 2019 as station improvements continue. During construction, the station will remain open and accessible to all customers.

Where do I catch my bus or SkyTrain?

Two new bus shelters at the Joyce-Collingwood Station – opening August 13.

 

Beginning August 13, customers will use the east stationhouse and newly-constructed bus loop to access SkyTrain and buses.

  • Buses will move to the new bus loop adjacent to the east stationhouse.
  • From August 13 to spring 2019, the west stationhouse will close and customers can catch their bus at the new bus loop adjacent to the east stationhouse.
  • The bus loop has larger shelters and is the new permanent location for the 28 and 41/43 routes.

 

Una estación mas y llego. Después de una tarde Diferente 😜

A post shared by Diego Alonso 🇨🇱 (@sanktus) on

Read more »

Modified weekend SkyTrain service at Joyce–Collingwood Station begins June 1

Photo of Joyce–Collingwood Station

SkyTrain service at Joyce–Collingwood Station will be modified on weekends, beginning June 1 and until the fall.

SkyTrain’s Expo Line is more than 30 years old and work is underway across the network as part of the TransLink Maintenance and Repair Program to keep our customers moving.

The platform tiles at Joyce–Collingwood Station have reached the end of their design life, so we’re replacing them as part of the Phase 2 station upgrades! The project is expected to take approximately 16 weeks with work taking place on weekends only.

Starting June 1, the westbound platform (Platform 1 to Waterfront) at Joyce–Collingwood Station will close on weekends from 9 p.m. on Friday until the start of service on Monday so this work can begin.

During work times on weekends, westbound Expo Line service will operate “skip-stop service” through the station. This means trains towards Waterfront from Patterson will skip Joyce–Collingwood and head directly to 29th Avenue Station. Eastbound trains on Platform 2 to King George or Production Way–University will operate normally and stop at Joyce–Collingwood Station.

Customers travelling westbound to and from Joyce–Collingwood Station will need to use Patterson or 29th Avenue Station to access Joyce–Collingwood.

If you’re travelling westbound from Joyce–Collingwood Station towards Waterfront Station, take an eastbound train from Platform 2 to Patterson Station. From there, board a westbound train from Platform 1 to Waterfront.

Skip-stop service westbound from Joyce

If you’re travelling westbound to Joyce–Collingwood Station, your train will skip Joyce–Collingwood and stop at 29th Avenue Station. From there, board an eastbound train from Platform 2 back to the open eastbound platform (Platform 2) at Joyce–Collingwood Station.

Skip-stop service westbound to Joyce

Customers should add 10-15 minutes to their travel time as a result of changes to service. Listen to on-train announcements, follow the signage and ask a SkyTrain Attendant if you need assistance.

Later in the summer, when the work at the westbound platform is complete, the eastbound platform (Platform 2 to King George or Production Way–University) will close on weekends for re-tiling and the Expo Line will operate skip-stop service eastbound through Joyce–Collingwood Station.

Author: Allen Tung

Q&A: Bike Parkades support active transportation in Metro Vancouver

Derek Yau is a transportation engineer with TransLink. He looks after the region’s bike facilities.

Did you know 107,000 trips are made each day by cycling in Metro Vancouver?

As Metro Vancouver’s transportation authority, it’s our job to help support and grow the number of bike trips. How do we do this? We help provide connections to the wider transportation system of the region by making transit more bike-accessible.

The Bike Parkade at Joyce–Collingwood Station on opening day

That means including spaces on transit for bicycles, managing the Major Road Network (including five bridges), providing cycling options such as the BC Parkway, Central Valley Greenway and Canada Line Pedestrian–Bicycle Bridge, and developing the Regional Cycling Strategy.

We also invest in Bike Parkades—indoor facilities where registered customers can store their bikes for the day and connect directly to transit. The latest facility opened at Joyce–Collingwood Station just last month, joining the parkades at Main Street–Science World and King George stations.  Read more »

Year in Review: an update on the Expo Line SkyTrain station upgrades

A major milestone for Metrotown Station this year as both the centre and west stationhouses opened!

It’s the most wonderful time of the year! A time to look back at the past twelve months and take stock of all that we’ve accomplished…like making tremendous progress on four Expo Line SkyTrain Station upgrades!

In order to ensure we continue to meet the needs of our customers and the entire region for years to come, these four stations are currently being upgraded to improve station accessibility, capacity, safety and security. Read more »