The elevator has been completely removed at the platform level of Broadway Station! [1]

The elevator has been completely removed at the platform level of Broadway Station in July!

Here’s the latest update on the Broadway Station upgrade project [2], for June-August 2009! (If you hadn’t heard, we are upgrading Broadway Station to better handle customer traffic and improve security: see this post [3] for the full details.)

What work was done in June 2009?

Steel work and framing for the new stairs at the south side entrance was completed in June. [4]

Steel work and framing for the new stairs at the south side entrance was completed in June.

What work was done in July 2009?

What’s happening in August 2009?

The interior of the station on the south side concourse. Floor tiles are being installed! [6]

The interior of the station on the south side concourse. Floor tiles are being installed!