First phase of running rail replacement work complete!

First phase of running rail replacement work complete!

https://youtu.be/8w64CC6yx34

You may have noticed in the past few months that the Expo Line has been undergoing some major maintenance work!

As part of that maintenance, we have been replacing major sections of rail along the 30 year old track.

The first phase of the work began last August and has just been completed – replacing 4,550 linear metres of rail at three locations.

Here’s what has been replaced so far:

  • 700 linear metres of rail along the outbound curve east of Edmonds Station
  • 950 linear metres of rail along the inbound curve west of Edmonds Station
  • 2,900 linear metres of rail along the S-curve between Commercial–Broadway and Main Street –Science World stations.

We will be continuing the rail replacement work this summer.

This work is critical to keeping our system in a good state of repair.

Thanks for your patience while we complete this necessary maintenance on the SkyTrain system!

Author: Jordan Keim