Knight Street Bridge Inspection
Knight Street Bridge Inspection
Heads up to all late Knight Street Bridge users! From Nov. 1 to 5 10 15/16 and Dec. 5 to 7 the Knight Street Bridge will undergo inspections to ensure a state of good repair. The bridge will remain open during the inspection however some lane closures will be required between 10 p.m. to 5 a.m on the following days (Please note dates and times have been updated, and all work is tentative due to being dependent on weather):
**UPDATE NOVEMBER 17:
- Tuesday, November 15, 2016
– One night, slow/curb lane closure northbound over the length of the north brance structure and Marine Drive Overpass - Wednesday, November 16, 2016
– One night, slow/curb lane closure northbound 230 metres of the south branch structure - Thursday, November 17, 2016
– One night, slow/curb lane closure northbound 230 metres of the south branch structure
November 1st
and 2nd– single lane closure southbound (completed)November 3rd
and 4th–single lane closure northboundslow/curb lane closure southbound over the length of the south branch structure (tentative)December 5th to 7th – Two nights, slow/curb lane closure for entire corridor length (all three sections) each night between 10 PM and 5AM.
Update:
Snooper Truck Inspection on Marine Drive Overpass, Knight Street Bridge North Branch and South Branch (Dec 12-14 between 10pm-5am)
Monday, Dec 12 – Knight Street Corridor Southbound Slow lane closure
Tuesday, Dec 13 – Knight Street Corridor Northbound Slow lane closure
Wednesday, Dec 14 – Knight Street Corridor Southbound Slow lane closure
Thursday, Dec 15 – Knight Street Corridor Northbound Slow lane closure
Motorists can expect minor delays during the lane closures, so if you`re driving, make sure to watch out for the closure and remember to obey all posted signs and instructions. We thank everyone for their patience while we do this important work.